Delhi Metro To open Its Phase 4 Priority Corridors By 2026: Details

-

- Advertisment -spot_img


The Delhi Metro Rail Corporation (DMRC) announced on Sunday that it is rapidly advancing with its Phase 4 expansion, aiming to open all three priority corridors comprising 65 kilometers of new lines by 2026.

In a post on X, DMRC said that over 50 percent of the work on these corridors has been completed. Specifically, the Majlis Park-Maujpur section has reached about 80 percent completion in civil work. Tunneling is ongoing on the Aerocity-Tughlakabad (Golden Line) and Janakpuri West-RK Ashram Marg (Magenta Line) corridors.

Regarding delays in the project, DMRC explained that despite beginning Phase 4 in December 2019, the project faced significant delays from 2020 to 2022 due to the COVID-19 pandemic and challenges in obtaining tree-cutting permissions. The DMRC noted that substantial work on the project has been ongoing for the last one and a half to two years, aiming for completion by 2026.

The section from Janakpuri West to Krishna Park Extension is nearly finished and is expected to open by August 2024, with the Majlis Park-Maujpur corridor also slated for completion next year. Other sections will open gradually by 2026.
However, the DMRC is still awaiting certain permissions related to tree-cutting and land acquisition at specific sites. High-level site visits are being conducted to expedite the work, and the necessary tree-cutting approvals are actively being pursued. Additionally, two new corridors, Inderlok-Indraprastha and Saket G Block-Lajpat Nagar, have recently received approval.
“The project is being monitored at various levels on a day to day basis. Site visits are also taken up at the highest level to expedite the work. Tree cutting permissions are being pursued at appropriate levels.” said DMRC in an official statement.
The DMRC is currently securing statutory clearances, including land acquisition, and is in the process of planning and tendering for further civil works, ensuring the project remains on track for its 2026 completion target. 



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest news

Death Toll in 1999 Columbine School Shooting Climbs to 14 With Homicide Ruling

For more than a quarter of a century, the death toll in the Columbine High School mass shooting,...

Felice Picano, Champion of Gay Literature, Is Dead at 81

Felice Picano, who in the 1970s and ’80s helped usher in a golden age of gay literature as...

Federal Cuts Prompt Johns Hopkins to Cut More Than 2,000 Workers

Johns Hopkins University, one of the country’s leading centers of scientific research, said on Thursday that it would...
- Advertisement -spot_imgspot_img

Selma Miriam, Founder of the Feminist Restaurant Bloodroot, Dies at 89

Selma Miriam and Noel Furie were unhappy housewives, as they put it, when they met at a gathering...

Trump downplays China-Russia-Iran nuclear talks, says they may discuss ‘de-escalation’

President Donald Trump, speaking from the Oval Office Thursday, downplayed an upcoming nuclear summit in Beijing between...

Must read

New country album pays homage to Tom Petty

New country album pays homage to Tom Petty...

At least 10 shot dead as section of Kenyan parliament set on fire

At least ten people were shot dead in...
- Advertisement -spot_imgspot_img

You might also likeRELATED
Recommended to you